Chapter 33 · Finish Carpentry DesignerBeta

Sample Office Building, Level 1, interior finishes: 13 finish codes on 11 rooms, wood panels, FRP, wall protection and the exit stair rails

From the designer's second commercial sample: the same office floor as chapter 31, now with the architect's finish legend and room finish schedule. Maple base, casing, stools and chair rail; sequence-matched wood panels and a slat ceiling in the lobby; a slat wall in the conference room; FRP in the restrooms and the janitor room; high-impact panels, a crash rail and corner guards in the corridor; the exit stair handrails and guard with their ADA checks; the finish class and combustible trim flags; the backing plan for the GC; the commercial lines for the BidRidge quote; and the Submittal set.

In the Finish Carpentry Designer, tap Open project and pick the sample file: it opens as the office floor's interior finishes in this chapter.

Narrated walkthrough, 2:12. Captions on.

The sample in numbers

  • Finish codes
    13
    trim, panels, wall protection, a slat ceiling
  • Rooms
    11
    on the room finish schedule (10 drawn, 1 typed)
  • Panels
    1,838 sf
    wood 599.8 · FRP 699 · high-impact 420 · slat 119.6
  • Install hours
    376.6
    26 BidRidge lines · $63,481 priced in the designer
  • Backing
    279.2 LF
    B1 to B4, by the GC
  • Sheets
    15
    Submittal set, ARCH D (19 shop sheets)

Step by step

Step 1: Open the interior finishes sample in the Finish Carpentry Designer

Step 1: Open the interior finishes sample

Open the Finish Carpentry Designer, tap New design, then Office building, level 1: interior finishes (commercial). The project type is Commercial, so the finish legend, the room finish schedule, the handrails, guards and wraps, and the finish takeoff show under the door schedule. Under Project, the occupancy (B, E, M, R-1) and Sprinklered pick the finish class each room needs; Backing and blocking is by the GC, so the designer draws the backing plan for them.

Field tip: The sample's names and sizes are made up. Residential projects never show any of this; their trim, lists and drawings are as before.

Step 2: The finish legend in the Finish Carpentry Designer

Step 2: The finish legend

Commercial: the Finish legend holds the architect's codes, 13 here: WB-1 maple base, RB-1 resilient base (by others), WC-1 casing, ST-1 stools, CH-1 chair rail, CR-1 crash rail, CG-1 corner guards, WP-1 high-impact wall panels, FRP-1 and FRP-2, AWP-1 rift white oak panels, SW-1 a slat wall and SC-1 a slat ceiling. Each code carries its size, species, finish, AWI grade (Economy, Custom, Premium or per the project specs), its flame-spread class and who installs it, and adds up its quantity and rooms.

Field tip: Generic codes: the product and its maker come from the specification. Tap a tag to edit it.

Step 3: The room finish schedule in the Finish Carpentry Designer

Step 3: The room finish schedule

The Room finish schedule lists 11 rooms: the 10 drawn on the plan (Add the drawn rooms) and Training 160, typed for the east wing that isn't drawn. Each row picks its base, casing, rail, crown, stool, walls, ceiling, protection and corner guards from the legend, and shows the class it needs. The heading sums it: 11 rooms, 376.8 install hours, $63,494 of material priced in the designer.

Field tip: A drawn room takes its trim from its codes, so its runs, copes, cut list and elevations follow; a typed room counts its trim from its perimeter.

Step 4: Import the architect's schedule in the Finish Carpentry Designer

Step 4: Import the architect's schedule

Import a finish schedule takes the architect's table pasted from a spreadsheet or a PDF (tab- or comma-separated, heading row first). Read the table guesses each column from its heading (Room number, Room name, Base, Walls); fix any guess, then Add the rooms. A code that isn't in the legend yet (RB-9 here) is added to it to fill in. New in 1.64: Read schedules in Plan background reads the room finish schedule straight off a vector PDF sheet (no AI) and adds the rooms here, linked to the drawn rooms with the same number or name.

Field tip: Check what each column is before you add the rooms: the guess comes from the heading.

Step 5: Panels on the walls in the Finish Carpentry Designer

Step 5: Panels on the walls

Each wall with a panel code is laid out on its elevation. The lobby's AWP-1 wood panels are 18 panels set in sequence on clips (599.8 sf), the conference room's slat wall 75 slats (119.6 sf), the corridor's high-impact panels 28 sheets to 48 in. with 293.3 LF of trims (420 sf), and the FRP 699 sf: FRP-1 to 48 in. over gypsum board in the restrooms, FRP-2 full height over block in the janitor room, with their division bars, corners and end caps.

Field tip: FRP and high-impact panels follow the maker's adhesive, trims and fastener pattern; the elevations show the sheet joints.

Step 6: Wall protection, ceilings and wraps in the Finish Carpentry Designer

Step 6: Wall protection, ceilings and wraps

Wall protection and ceilings: the corridor's CR-1 crash rail is 105 LF at 33 in. with 28 end caps and corners, and CG-1 is 4 corner guards; the lobby's SC-1 slat ceiling is 440 sf. Column wraps, stools and stations: CW-1 wraps the 2 lobby columns (108 sf, 24 LF of base and cap), SF-1 is 18 LF of ST-1 stool at the storefront, and the reception desk's die wall trim stays with the casework sub.

Field tip: Corner guards moved here from the Division 10 Designer's out-of-scope list: they are a finish carpentry line now.

Step 7: Handrails and guards in the Finish Carpentry Designer

Step 7: Handrails and guards

Handrails, guards and wraps: HR-1 runs on both sides of the S1 exit stair, 1 1/2 in. round, 1 1/2 in. clear of the wall on brackets 4 ft apart with a 2 in. arm, a 12 in. top extension. That is 67.4 LF (41.9 on the walls, 25.5 on the guard), 4 returns and end caps and 13 brackets, and a 23.4 LF guard with 2 3/8 in. openings. Its 11 checks pass, each with its section: ADA 2010 505.2 to 505.10.3 and 307.2, IBC 2021 1011.5.2 and the guard settings.

Field tip: Checks and flags, not a certification: the guard height and openings are job settings for the code official and the specifications.

Step 8: Finish class and combustible trim flags in the Finish Carpentry Designer

Step 8: Finish class and combustible trim flags

The checks add the finishes to the door checks: each code's class against the class the room needs (IBC 2021 Table 803.13: WP-1 Class B where Class C is asked passes, FRP-2 is Class A) and the share of each wall covered by wood trim (IBC 2021 806.7, 10 percent at most). Offices 101 and 102 come out at 13.2% and Conference 103 at 17.3%, flagged to review with the code official, next to the door checks from chapter 31: nothing to fix, 3 to review, 94 passing.

Field tip: Table 803.13 is read as adopted and sprinklered, footnotes not applied: confirm the classes with the code official.

Step 9: The backing plan in the Finish Carpentry Designer

Step 9: The backing plan

Backing and blocking is the GC's, before the drywall, so the designer lists it: B1 and B4 at 5 3/4 to 9 1/4 in. and 104 1/4 to 107 3/4 in. for the AWP-1 clip rows (66 LF each), B2 at 28 to 35 in. for the HR-1 brackets on the stair walls (41.9 LF) and B3 at 32 to 40 in. for the CR-1 crash rail (105 LF). The Backing plan sheet draws them on the floor plan with their tags.

Field tip: Show the backing on the plan (Rooms) and the elevations (Walls) with the box under the table.

Step 10: The BidRidge lines in the Finish Carpentry Designer

Step 10: The BidRidge lines

BidRidge lines (Finish carpentry): 26 lines go to the quote on one Interior finishes row, beside the door row from chapter 31: handrails, fittings and guards, column wraps, the base, casing, stools and chair rail by the schedule with their copes and the premium-grade fitting, the slat wall, high-impact panels and trims, wood panels set in sequence, FRP and its trims, the slat ceiling overhead, crash rails and corner guards. 376.8 hours in all, and the $63,494 of material priced in the designer in three lines.

Field tip: Hours each are the BidRidge Finish carpentry trade's starting rates; set yours there.

Step 11: The Submittal set in the Finish Carpentry Designer

Step 11: The Submittal set

Drawing set, Sheets for: Submittal set. The full set on ARCH D has 15 sheets: the cover and the door sheets from chapter 31, then FC-6 Finish plan, FC-7 Room finish schedule (with the legend), FC-8 Trim takeoff, FC-9 to FC-12 Elevations: panels and wall protection, FC-13 Backing plan and FC-14 Details (frame, threshold, trim profiles, the handrail and guard, FRP and high-impact corners, the panel reveal on clips, the crash rail and corner guard). The 11x17 shop set has 19 sheets, typical details first.

Field tip: The Submittal set is download only: Save PDF. It is never added to the BidRidge job.

What you get

The drawing set, the lists and the files

Real files from this sample, made by the designer. Tap a page to see it full size. Yours carry your company, the client and the address.

FC-0 Cover sheet and sheet index
FC-0 Cover sheet and sheet index
FC-6 Finish plan: each room's codes
FC-6 Finish plan: each room's codes
FC-7 Room finish schedule and finish legend
FC-7 Room finish schedule and finish legend
FC-9 Elevations: panels and wall protection (1)
FC-9 Elevations: panels and wall protection (1)
FC-13 Backing plan
FC-13 Backing plan
FC-14 Details
FC-14 Details
Submittal (11x17 shop) FC-1 Typical details
Submittal (11x17 shop) FC-1 Typical details
Submittal (11x17 shop) FC-10 Finish legend
Submittal (11x17 shop) FC-10 Finish legend

More in the guide

Try it on your own job

Open the sample, change it to your measurements, and send it to a BidRidge quote. Drawing is free; the drawing set, the lists and the quote come with a BidRidge license or the 14-day trial.

In the Finish Carpentry Designer, tap Open project and pick the sample file: it opens as the office floor's interior finishes in this chapter.

Sample designs: names, sizes and clients are made up. Prices are BidRidge's starting rates; set your own. The designers check against common guidelines (IRC, NKBA and the makers' published numbers) to help you catch mistakes. They don't replace your building department or the manufacturer's installation instructions: verify with them.