BidRidge › Designers › Guide › Chapter 38

Chapter 38 · Concrete DesignerBeta

Sample Office Building, 3 stories: 21,840 sf of slab on metal deck on three floors, 1344 + 96 shear studs, a formed entry canopy, pan stairs and pads

From the designer's third commercial sample: a made-up three-story steel-frame office. The floors above grade are drawn one at a time from the structural plans: slabs on 2 in. composite deck on levels 2 and 3 (level 2 in two pours), a 3 in. deck penthouse floor, the stair, elevator and shaft openings, and a formed slab-and-beam entry canopy on two columns. The concrete comes from the deck profile you type (the flute plus the topping), with a deflection and ponding allowance; studs, pour stops, closures, construction joints, shoring, pan stairs and pads are counted, checked and sent to the BidRidge quote.

Narrated walkthrough, 1:25. Captions on.

The sample in numbers

  • Slab on metal deck
    309.52 CY
    21,840 sf on 3 floors, flute + topping + 7% deflection / ponding
  • Shear studs
    1440
    1344 furnished and welded, 96 weld only
  • Pour stops
    1,254 LF
    632 LF of flute closures, 120 LF of construction joints
  • Formed canopy
    9.39 CY
    413.3 sf of forms, 4,200 sf-days of shores
  • Reinforcing as drawn
    3.95 tons
    22,704 sf of welded wire
  • Sheets
    18
    Submittal set, ARCH D (19 on the 11x17 shop set)

Step by step

Step 1: Open the office sample in the Concrete Designer

Step 1: Open the office sample

Open the Concrete Designer, tap New design, then Sample Office Building, 3 stories. It opens as a Commercial project on All floors: the level 1 slab on grade and each floor's slabs side by side, every plan titled with its slab count. The Plan bar over the drawing switches between All floors, Site / ground and each floor: Level 2, Level 3 and the Penthouse floor. A floor shows its own elevated slabs, openings and columns over the building outline and the gridlines, and only the elevated tools.

Field tip: The sample's names and sizes are made up. A design that never uses elevated slabs saves and prices exactly as before.

Step 2: Draw a floor's slabs in the Concrete Designer

Step 2: Draw a floor's slabs

On Level 2, Elevated slab draws a slab outline from the structural plans (drag a rectangle or tap the corners). Level 2 is two slabs, west and east, in two pours: where they meet the designer draws a construction joint (120 LF in the sample with the canopy edge), everywhere else a pour stop. The light lines show the deck ribs and the arrow their direction; Slab opening draws the stair, elevator and shaft openings (pour stop around each) and blockouts poured later.

Field tip: Draw each pour as its own slab when the structural plans show a pour break: the construction joint is counted once, the pour stop only on the free edges.

Step 3: The deck profile sets the concrete in the Concrete Designer

Step 3: The deck profile sets the concrete

Each slab on deck takes a profile, the total thickness, the gauge and the rib direction. On the sample's 2 in. deck at 5 1/4 in. total, the flute adds 1 in. and the topping is 3.25 in.: 1.31 CY a 100 sf. DS1, level 2 west, is 5,136 sf after its openings: 67.37 CY, 72.09 CY with the 7% deflection and ponding allowance; the order waste stays on the pour.

Field tip: Concrete a sf = rib depth x the average flute width / the rib spacing, plus the topping (the total less the rib depth).

Step 4: Profiles, checks and the rest of the floor in the Concrete Designer

Step 4: Profiles, checks and the rest of the floor

Under Project, Elevated slabs holds the floors, the deck profiles (1 1/2, 2 and 3 in. composite deck presets, labeled typical), the deflection and ponding %, normal or lightweight concrete, and the numbers the checks use: the minimum topping over the ribs, the topping the UL design on the drawings asks for at the fire rating, the cover over the welded wire, and the pour stop gauge. Pan stairs (fill per tread and landing), pads on the decks and the allowances (post-tensioned slabs and tilt-up panels by a sub, shoring engineering, testing and inspection) are typed here too.

Field tip: The profiles are typical numbers only: type the deck maker's rib depth, spacing and flute widths for the deck on your drawings.

Step 5: Studs, bars and pour stops as drawn in the Concrete Designer

Step 5: Studs, bars and pour stops as drawn

Studs are typed per beam or as a total, furnished and welded or weld only (1344 and 96 in the sample). Reinforcing is welded wire or bars each way as drawn, with the negative-moment bars over the girders; the card shows the elevated slab schedule, the profiles with the concrete each gives, the formed slabs and shoring, the columns, the openings, the pan stairs and pads, and 3.95 tons of bars as drawn.

Field tip: Everything is counted from the structural drawings: the designer never designs a slab, a deck or a bar.

Step 6: A formed slab with shores in the Concrete Designer

Step 6: A formed slab with shores

The entry canopy is a formed slab and beam: an 8 in. slab with B1 16 x 16 in. below it, top and bottom mats, on two 16 x 16 in. columns. The designer counts the deck forms, the beam sides and bottom and the edge forms (413.3 sf of contact), the shores for the days set, the reshores below when there are floors under it, and the columns' concrete, forms and bars. A formed or shored slab also gets a shore layout: shores on a grid (4 x 4 ft to start, set under Elevated slabs > Shoring), stringer lines, joists, plyform sheets, extra shores under the beams and the reshores below; a column group picks its forms (job-built plywood with clamps, rental steel, fiber tube or rental round forms) and the form sets to reuse. The Formwork and shoring equipment table lists the shores, stringers, joists, sheets, reshores, column forms, clamps, chamfer and braces for the crew and the rental order (a typical layout: the formwork engineer's governs; the priced lines stay the contact sf and the shoring sf-months). The Sample Clinic, 2-story concrete frame shows it all: formed slabs on Level 2 (drop panels) and the roof, 20 columns a floor, 10 plywood form sets reused.

Field tip: Forms, shoring and reshoring are the contractor's means and methods: the designer counts them for the price and flags them for a qualified engineer.

Step 7: The checks in the Concrete Designer

Step 7: The checks

The checks flag a topping over the ribs under the minimum or under the UL design's topping (typed, or the default for the rating and concrete: UL D925 over unprotected deck to 3 h, UL D739 over a protected deck at 4 h; with a fix that sets the thickness), show the IBC 722.2.2.1.3 slab thickness against Table 722.2.2.1 as a cross-check, welded wire set too high or below the top of the ribs, and a deck span over the maximum unshored span typed from the deck maker's table (with a fix that marks the slab shored). They note the pour stop gauge to check against the maker's pour stop table, lightweight concrete, and the shoring note.

Field tip: Flags only: the structural drawings and the deck maker's data govern.

Step 8: Send it to BidRidge in the Concrete Designer

Step 8: Send it to BidRidge

The BidRidge template carries 22 elevated slab lines: the deck and formed slab concrete, welded wire, reinforcing in tons, studs, pour stops, closures, construction joints, openings, place and finish, 6 elevated pumps, columns, pan stair treads and landings, pads, forms, shoring rent and hours, and the allowances. FF / FL, wet cure and the hardener, sealer and polished finishes on the decks join the part 1 lines.

Field tip: The elevated pours price on their own pump line; the slab on grade keeps the usual pump line.

Step 9: The Submittal set in the Concrete Designer

Step 9: The Submittal set

Drawing set > Sheets for > Submittal set adds a slab plan for each floor (slabs by pour, pour stops, construction joints, rib direction, openings, columns) and a formwork and shoring plan for each floor with formed or shored slabs or column forms (the shores, stringer lines, drop panels and columns), the elevated slab, profile, formed slab and shoring, column, formwork and shoring equipment, opening and pan stair schedules, the reinforcing as drawn, and the sections: the typical slab on deck with the studs in the ribs, the pour stop at the slab edge and at an opening, the construction joint, the formed slab and beam with shores, the column form, the pan stair fill and the pad on the deck. 18 ARCH D sheets, or 19 11x17 shop sheets.

Field tip: The Submittal set needs Commercial, like the other commercial sheets of this designer.

What you get

The drawing set, the lists and the files

Real files from this sample, made by the designer. Tap a page to see it full size. Yours carry your company, the client and the address.

Submittal (ARCH D) C-3 Level 2 slab plan
Submittal (ARCH D) C-3 Level 2 slab plan
Submittal (ARCH D) C-9 Elevated slab schedule
Submittal (ARCH D) C-9 Elevated slab schedule
Submittal (ARCH D) C-10 Deck profile schedule
Submittal (ARCH D) C-10 Deck profile schedule
Submittal (ARCH D) C-17 Sections
Submittal (ARCH D) C-17 Sections
Submittal (11x17 shop) C-1 Typical details
Submittal (11x17 shop) C-1 Typical details
Submittal (11x17 shop) C-2 Typical details (cont.)
Submittal (11x17 shop) C-2 Typical details (cont.)
Submittal (11x17 shop) C-6 Level 3 slab plan
Submittal (11x17 shop) C-6 Level 3 slab plan
Submittal (11x17 shop) C-13 Formed slab and shoring schedule
Submittal (11x17 shop) C-13 Formed slab and shoring schedule

More in the guide

Try it on your own job

Open the sample, change it to your measurements, and send it to a BidRidge quote. Drawing is free; the drawing set, the lists and the quote come with a BidRidge license or the 14-day trial.

Sample designs: names, sizes and clients are made up. Prices are BidRidge's starting rates; set your own. The designers check against common guidelines (IRC, NKBA and the makers' published numbers) to help you catch mistakes. They don't replace your building department or the manufacturer's installation instructions: verify with them.